Contracting Company JSC MSU-90 Started Assembling the Dome Part of the Reactor Building Inner Containment at Power Unit 2 of the LNPP under Construction
|
2018-02-13 |
|
Low Pressure Cylinder Rotor Delivered to the Power Unit 2 Turbine Building of the Leningrad NPP under Construction
|
2018-02-12 |
|
JSC MSU-90 Continues Installing Reactor Plant Equipment on the LNPP Construction Site
|
2018-02-08 |
|
Aleksandr Tupitsyn, the Hanhikivi-1 NPP Construction Director in JSC CONCERN TITAN-2, Delivered Reports at the Polytechnic University of Milan
|
2018-02-07 |
|
The New Power Unit Reactor of LNPP has been Brought to the Minimum Controlled Power Level Today
|
2018-02-06 |
|
JSC SEM Prepares to Start Welding Reactor Coolant Pipelines
|
2018-02-02 |
|
JSC Sosnovoborelektromontazh Installs a Modern Lighting System on Sosnovy Bor Schools Facades.
|
2018-02-01 |
|
JSC MSU-90 Continues Extensive Works in the Power Unit 2 Turbine Building of LNPP under Construction
|
2018-01-31 |
|
The Veterans of the Nuclear Society of Finland (ATS Senior) Visited the Construction Site of the New LNPP Power Units
|
2018-01-30 |
|
Northern Construction Department Completed Concreting Part of Inner Containment of Reactor Building at Power Unit 2 of LNPP under Construction.
|
2018-01-26 |
|
TEREX Tower Crane Telescoping is under Way on LNPP Power Unit 2 Construction Site
|
2018-01-25 |
|
Northern Construction Department Prepares for Further Concreting of Evaporative Cooling Tower at LNPP-2 Construction Site
|
2018-01-16 |
|
Holding Company Subsidiaries Assemble Inner Containment Dome Liner of Reactor Building for Power Unit 2 of LNPP-2
|
2018-01-15 |
|
Generator Stator Installed in the Turbine Building of the Power Unit 2 of the Leningrad NPP under Construction
|
2017-12-29 |
|
Nuclear Fuel Loading into Reactor Completed in the Power Unit 1 of LNPP-2
|
2017-12-18 |
|
“Safety Culture Day” at the Hanhikivi-1 NPP Construction Site
|
2017-12-12 |
|
The Reactor First Criticality Started at Power Unit 1 of the Leningrad NPP
|
2017-12-08 |
|
PJSC SUS Team Completed Assembling the Polar Crane Elements for the Reactor Building of the Power Unit 2 of the Leningrad NPP under Construction.
|
2017-12-06 |
|
JSC SAM Fourth Unit Specialists Reconstructing 330 kV Overall Plant Switchgear of LNPP-1
|
2017-12-04 |
|
Holding Company Subsidiaries’ Teams Carried out Unique Installation Operation at the LNN Construction Site.
|
2017-11-30 |
|
Nuclear Construction Conference Held in Moscow.
|
2017-11-29 |
|
Four New Radiation Monitoring Points Installed in Sosnovy Bor
|
2017-11-27 |
|
JSC SEM Experts Carry out Works in Power Unit 1 of the LNPP under Construction
|
2017-11-24 |
|
The Delegation from Finnish Twin Cities of Pyhäjoki, Kalajoki, and Raahe Arrived in Sosnovy Bor
|
2017-11-23 |
|
TITAN-2 Holding Company Once Again Became One of Top-50 Most Fast-Growing Russian Companies
|
2017-11-17 |
|
Reactor Vessel for the Power Unit 2 of the Leningrad NPP under Construction Delivered to Sosnovy Bor from Izhora Plants
|
2017-11-15 |
|
Power Unit 1 of the Leningrad NPP under construction being prepared for the reactor first criticality.
|
2017-11-13 |
|
Physical Protection Facilities of the New LNPP Power Units Transferred to National Guard Forces.
|
2017-11-09 |
|
Memorial Stone installed at the Regional Volleyball Center Construction Site in Sosnovy Bor
|
2017-11-07 |
|
Northern Construction Department Team Continues Works in the Reactor Building at the Power Unit 2 of LNPP under Construction.
|
2017-11-03 |
|
French nuclear construction experts came with a visit to learn the experience of the JSC "CONCERN TITAN-2"
|
2017-11-01 |
|
Izhora plants shipped the reactor vessel for the Power Unit 2 of the Leningrad NPP under construction
|
2017-10-31 |
|
JSC "MSU-90" continues to install the turbine unit components at the Power Unit 2 of the Leningrad NPP under construction.
|
2017-10-25 |
|
Hanhikivi-1 NPP site began testing concrete mixes
|
2017-10-23 |
|
Northern Construction Department started preassembling polar crane components and preparing for installation
|
2017-10-20 |
|
The court ruled in favour of JSC CONCERN TITAN-2 on a case of more than half a billion rubles
|
2017-10-19 |
|
Work is ongoing in the reactor building at the second Power Unit of the Leningrad NPP under construction
|
2017-10-11 |
|
Subsidiaries of the TITAN-2 holding took part in discussion of implementation of the ROSATOM production system (PSR)
|
2017-10-06 |
|
Sosnovy Bor began preparations for the construction of the regional volleyball center
|
2017-10-03 |
|
Power Unit 1 equipment is under inspection at the LNPP being constructed, prior to the reactor first criticality
|
2017-10-02 |
|
Employees of JSC MSU-90 completed lifting operations of all large-size tanks and vessels in the water treatment building at Power Unit 2 of the LNPP under construction
|
2017-09-29 |
|
Installation of turbine set started in the turbine building of Power Unit 2 of the LNPP under construction
|
2017-09-27 |
|
Specialists of subsidiary companies of the holding "TITAN-2" installed the pressurizer at Power Unit 2 of the LNPP under construction
|
2017-09-25 |
|
One of the four steam generators was mounted at Power Unit 2 of the LNPP under construction
|
2017-09-19 |
|
Finnish partners visited JSC CONCERN TITAN-2
|
2017-09-18 |
|
Specialists of "Northern construction department" are working on the roof of the reactor building of Power Unit 1 of the Leningrad NPP under construction
|
2017-09-11 |
|
Buildings at the construction site of Leningrad NPP are being clad with thermopanels
|
2017-09-07 |
|
Specialists of subsidiary companies of the holding TITAN-2 prepare for commissioning the turbine condensers cooling system of Power Unit 1 of the LNPP under construction
|
2017-09-04 |
|
The works in office, amenity and laboratory building of the Leningrad NPP under construction are ending
|
2017-09-01 |
|
Specialists of the contractors of the holding prepare workshop area for commissioning
|