Generator Stator Installed in the Turbine Building of the Power Unit 2 of the Leningrad NPP under Construction
|
2017-12-29 |
Nuclear Fuel Loading into Reactor Completed in the Power Unit 1 of LNPP-2
|
2017-12-18 |
“Safety Culture Day” at the Hanhikivi-1 NPP Construction Site
|
2017-12-12 |
The Reactor First Criticality Started at Power Unit 1 of the Leningrad NPP
|
2017-12-08 |
PJSC SUS Team Completed Assembling the Polar Crane Elements for the Reactor Building of the Power Unit 2 of the Leningrad NPP under Construction.
|
2017-12-06 |
JSC SAM Fourth Unit Specialists Reconstructing 330 kV Overall Plant Switchgear of LNPP-1
|
2017-12-04 |
Holding Company Subsidiaries’ Teams Carried out Unique Installation Operation at the LNN Construction Site.
|
2017-11-30 |
Nuclear Construction Conference Held in Moscow.
|
2017-11-29 |
Four New Radiation Monitoring Points Installed in Sosnovy Bor
|
2017-11-27 |
JSC SEM Experts Carry out Works in Power Unit 1 of the LNPP under Construction
|
2017-11-24 |
The Delegation from Finnish Twin Cities of Pyhäjoki, Kalajoki, and Raahe Arrived in Sosnovy Bor
|
2017-11-23 |
TITAN-2 Holding Company Once Again Became One of Top-50 Most Fast-Growing Russian Companies
|
2017-11-17 |
Reactor Vessel for the Power Unit 2 of the Leningrad NPP under Construction Delivered to Sosnovy Bor from Izhora Plants
|
2017-11-15 |
Power Unit 1 of the Leningrad NPP under construction being prepared for the reactor first criticality.
|
2017-11-13 |
Physical Protection Facilities of the New LNPP Power Units Transferred to National Guard Forces.
|
2017-11-09 |
Memorial Stone installed at the Regional Volleyball Center Construction Site in Sosnovy Bor
|
2017-11-07 |
Northern Construction Department Team Continues Works in the Reactor Building at the Power Unit 2 of LNPP under Construction.
|
2017-11-03 |
French nuclear construction experts came with a visit to learn the experience of the JSC "CONCERN TITAN-2"
|
2017-11-01 |
Izhora plants shipped the reactor vessel for the Power Unit 2 of the Leningrad NPP under construction
|
2017-10-31 |
JSC "MSU-90" continues to install the turbine unit components at the Power Unit 2 of the Leningrad NPP under construction.
|
2017-10-25 |
Hanhikivi-1 NPP site began testing concrete mixes
|
2017-10-23 |
Northern Construction Department started preassembling polar crane components and preparing for installation
|
2017-10-20 |
The court ruled in favour of JSC CONCERN TITAN-2 on a case of more than half a billion rubles
|
2017-10-19 |
Work is ongoing in the reactor building at the second Power Unit of the Leningrad NPP under construction
|
2017-10-11 |
Subsidiaries of the TITAN-2 holding took part in discussion of implementation of the ROSATOM production system (PSR)
|
2017-10-06 |
Sosnovy Bor began preparations for the construction of the regional volleyball center
|
2017-10-03 |
Power Unit 1 equipment is under inspection at the LNPP being constructed, prior to the reactor first criticality
|
2017-10-02 |
Employees of JSC MSU-90 completed lifting operations of all large-size tanks and vessels in the water treatment building at Power Unit 2 of the LNPP under construction
|
2017-09-29 |
Installation of turbine set started in the turbine building of Power Unit 2 of the LNPP under construction
|
2017-09-27 |
Specialists of subsidiary companies of the holding "TITAN-2" installed the pressurizer at Power Unit 2 of the LNPP under construction
|
2017-09-25 |
One of the four steam generators was mounted at Power Unit 2 of the LNPP under construction
|
2017-09-19 |
Finnish partners visited JSC CONCERN TITAN-2
|
2017-09-18 |
Specialists of "Northern construction department" are working on the roof of the reactor building of Power Unit 1 of the Leningrad NPP under construction
|
2017-09-11 |
Buildings at the construction site of Leningrad NPP are being clad with thermopanels
|
2017-09-07 |
Specialists of subsidiary companies of the holding TITAN-2 prepare for commissioning the turbine condensers cooling system of Power Unit 1 of the LNPP under construction
|
2017-09-04 |
The works in office, amenity and laboratory building of the Leningrad NPP under construction are ending
|
2017-09-01 |
Specialists of the contractors of the holding prepare workshop area for commissioning
|
2017-08-31 |
Employees of subsidiary companies of the holding TITAN-2 carry on works in the nuclear service building with utility rooms in the controlled access area
|
2017-08-29 |
JSC CONCERN TITAN-2 will construct a radioactive waste reprocessing facility for the Leningrad NPP
|
2017-08-25 |
Today JSC CONCERN TITAN-2 signed a contract for construction of a volleyball center in Sosnovy Bor
|
2017-08-25 |
Employees of the LNPP under construction, holding "TITAN-2" and other contractors started “hot” run of the reactor plant equipment of the new Power Unit of the Leningrad NPP
|
2017-08-17 |
Cooperation Agreement signed between Sosnovy Bor and the Finnish towns of Pyhäjoki, Kalajoki and Raahe
|
2017-08-17 |
Specialists of SMU-2 of "Northern Construction Department" continue construction of the third cooling tower at the construction site of the Leningrad NPP
|
2017-08-16 |
Grigory Naginsky, General Director of JSC "CONCERN TITAN-2" presented awards to employees of the company
|
2017-08-15 |
In Nizhny Novgorod, winners of the State Corporation "ROSATOM" contest: "Best in profession in capital construction complex of the nuclear industry" were awarded
|
2017-08-11 |
Rock material recycled at the construction site
|
2017-08-08 |
Student construction teams are working at the construction site of the Leningrad nuclear power plant
|
2017-08-07 |
Specialists of SMU-1 of "Northern Construction Department” carry on the work with the fourth tier of reactor inner containment of Power Unit 2 of the LNPP under construction
|
2017-08-03 |
Employees of subsidiaries of the holding "TITAN-2" are preparing themselves for the final of the contest "Best in profession in the capital construction complex of the nuclear industry"
|
2017-07-31 |
Specialists tested operation of evaporative cooling towers and two circulation pumps
|
2017-07-27 |