The work is carried out using in-house resources of JSC CONCERN TITAN-2.
The tracks run along the turbine building. They are intended to move the auxiliary standby transformers to their design locations. Transformers are part of the power supply system to the nuclear power plant equipment.
Once the installation is completed the tracks will be tested with load, then the area will be concreted.
Note:
Titan-2 Holding is the largest in the North-West group of companies, constructing the most important nuclear industry and power facilities. The company performs a full range of construction and installation works from engineering to commissioning.
Titan-2 Holding is the general contractor for the construction of the Leningrad NPP-2 power units. The Holding Companies perform all the civil, installation, and electrical works at a construction site. The works are carried out in the reactor, turbine, power supply, water supply, heat cogeneration buildings and other power unit structures.
The Holding is the main contractor for the construction of the Hanhikivi-1 NPP in Finland.