The works are being performed under the contract with JSC Concern Rosenergoatom.

This station will become the first facility built at the site of construction of two new power units of the Leningrad NPP with VVER-1200 reactors.

The winners were awarded in the International Exhibition Center “Kazan Expo” on 8th of October within the official ceremony of Championship closing.

Installation operation took around six hours. The vessel was placed at its design location in the reactor cavity using crawler crane Liebherr LR 13000.

TITAN-2 Holding acts as the General Contractor for construction of Power Units No. 3 and 4 of LNPP-2 (or Power Units No. 7 and 8 of LNPP).

The project is being implemented by Engineering Division of State Atomic Energy Corporation ROSATOM.

The first truss unit was installed on 5 July. Its weight was 170 t, precision of installation was 3 mm.

The operation has been done by specialists from the Russian-Turkish Joint Venture TITAN2 IC İÇTAŞ İNŞAAT ANONİM ŞİRKETİ (T2IC).

They were made at the construction base of LLC TITAN TECHNOLOGY PIPELINE (TPL) in Sosnovy Bor.