Works in various directions are actively in progress at the moment.
CONCERN TITAN-2 keeps handing over the systems to the Customer for pre-commissioning in the fabrication/refabrication unit. The main works relate to the ventilation, gas supply and electrical network systems.
The assembly of the pedestal in reactor unit BREST-OD-300 has been completed by the TITAN-2 specialists. All sections of the reactor vessel enclosure structure have been delivered to the construction site. Thesearethebottomandmiddlesupportingskirts
Construction workers have reached el. +8 in the turbine building. The planned works on the construction of walls, columns and floor slabs are in progress there. They have also started to erect the start-up boiler house. It is a special facility for the heating of the turbine building pipelines. The foundation slab is already arranged and the preparation for the exhaust stack foundation pouring is now in progress. Besides, the foundations for the 220 kV integrated GIS are ready and the works on the cooling tower framework arrangement are also completed.
All equipment installation and pre-commissioning works are in compliance with the schedules.
For information:
The TITAN-2 Holding is a Russian group of companies that builds nuclear facilities. Organisations of the Holding perform the whole cycle of works, from development of basic design documentation to facility commissioning.
The TITAN-2 Holding is the general contractor for construction of the new power units of the Leningrad NPP. At the construction site, the organisations of the Holding perform all civil construction, installation, and electric installation works.
The Holding participates in the construction of Akkuyu NPP in Turkey, Paks II NPP in Hungary and El-Dabaa NPP in Egypt.