300 cubic metres of concrete were used at concreting the foundation of the integrated pumping station of fire fighting water supply and automated fire fighting. This concrete is of high elasticity and resistance to frost and water.
“The concrete is perfectly suitable for construction of facilities in severe climatic conditions,” noted Konstantin Khudyakov, LNPP Facilities Program Director of JSC CONCERN TITAN-2”. “The pumping station foundation will maintain its strength far beyond the limits of design operational lifetime of new power units. Besides, the concrete is environment-friendly since is contains natural constituents. The hardened concrete mix is compatible with the natural stone and has no adverse impact on the human.”
The pumping station will become the first building out of the whole complex of facilities of LNPP new construction phase. It is intended for ensuring fire safety during the construction of power units Nos. 7 and 8. Station’s construction, installation, and pre-commissioning works are on schedule and will be completed in December of the next year.
For information:
The TITAN-2 Holding is a Russian group of companies that builds nuclear facilities. Organisations of the Holding perform the whole cycle of works, from development of basic design documentation to facility commissioning.
The TITAN-2 Holding is the general contractor for construction of the new power units of the Leningrad NPP. At the construction site, the organisations of the Holding perform all civil construction, installation, and electric installation works.
The Holding participates in the construction of Akkuyu NPP in Turkey, Paks II NPP in Hungary and El-Dabaa NPP in Egypt.
The works on concreting the pumping station foundation have commenced at the LNPP construction site
- Details