This year more than two hundred students from ten regions of Russia participate in Multiregional student construction – Atom for Peace LNPP-2018 project.
- Details
For the time being, the specialist of JSC MSU-90, subsidiary company of TITAN-2 holding, have performed 70% of the total welding scope.
- Details
The specialists of JSC MSU-90 and JSC CONCERN TITAN-2 performed the installation. The dome was installed to the height of more than 50 meters.
- Details
The extension is required to lift the reactor building dome on the second LNPP-2 power unit under construction.
- Details
The installation of the dome equipment will finish soon. After that, the structure will be installed onto the reactor building.
- Details
The installation was executed by the hoisting installation subdivision SMU-2 of JSC CONCERN TITAN-2. This subdivision is responsible for the assembly of all the cranes at LNPP-2 power units construction site.
The works on the polar crane in the reactor building took several months. The load trolley and maintenance portal of the crane were preassembled in the special area close to the reactor building. The weight of these assemblies was 102 and 10 tons respectively.
The specific design was made to move these components with Liebherr LR11350 crawler crane into the reactor building. Open-top method was used to move the components through the roof, which has not yet been closed with the dome. Two months earlier SMU-2 specialists performed the complicated installation of the polar crane beam weighing over 200 tons and 40 meters long. The load trolley and the maintenance portal were installed on this very beam.
Now the specialists proceed to the final assembly and commissioning works. After the reactor building is covered with the dome, the installation of the crane power supply system will commence.
Note:
Titan-2 Holding is the largest in the North-West group of companies, constructing the most important nuclear industry and power facilities. The company performs a full range of construction and installation works from engineering to commissioning.
Titan-2 Holding is the general contractor for the construction of the Leningrad NPP-2 power units. The Holding Companies perform all the civil, installation, and electrical works at a construction site. The works are carried out in the reactor, turbine, power supply, water supply, heat cogeneration buildings and other power unit structures.
The Holding is the main contractor for the construction of the Hanhikivi-1 NPP in Finland.
- Details
They covered 2000 kilometers in 5 days.
- Details
The specialists of JSC MSU-90 and JSC CONCERN TITAN-2 performed the installation.