The program of the meeting included an excursion to the facility under construction and a meeting on the further cooperation of the company with the public organization Russian Student Brigades.

The event was attended by representatives of JSC CONCERN TITAN-2, leaders of winter student construction projects in Sosnovy Bor and Kaliningrad, leaders of eleven construction brigades participating in the project, as well as Yuri Boldyrev, officer in charge for construction industry in the Russian Student Brigades Central Headquarters.

It is planned that CONCERN TITAN-2 will accept 300-400 students in its Kaliningrad Branch during the summer shift. Now, during the winter construction project, the youngsters are engaged in reinforcement and concreting work, and in summer, the most part of the work will be related to finishing. The meeting participants discussed issues that require intensive training for the one-time involvement of such a large number of staff. All the student construction brigade leaders expressed their desire to participate in the competitive selection for the summer project.

Today, at the construction site of JSC CONCERN TITAN-2 in the Kaliningrad region, 58 students are employed as part of five student construction brigades: “Caryatid” (Rostov region), “Prospect-15” (Republic of Chuvashia), “PSK-Master” (Nizhny Novgorod region) , “Tesla” (Republic of Tatarstan), “SHSO PGUAS” (Penza region).

CONCERN TITAN-2 provided the young constructors with everything necessary for the period of the winter construction project: accommodation, meals, transportation to their workplace. All students received special clothing, underwent briefings on occupational health and safety, electrical safety, work at heights and fire safety basics.

Note:

Titan-2 Holding is the largest in the North-West group of companies, constructing the most important nuclear industry and power facilities. The company performs a full range of construction and installation works from engineering to commissioning.

Titan-2 Holding is the general contractor for the construction of the Leningrad NPP-2 power units. The Holding Companies perform all the civil, installation, and electrical works at a construction site. The works are carried out in the reactor, turbine, power supply, water supply, heat cogeneration buildings and other power unit structures.

At the last stage of work, January 30 - 31, builders laid concrete from the elev. +68.750 to +70.200 on the structure dome portion. A total of 116 cubic meters of concrete were poured.

The work on the reactor building cast-in-situ structures is finished with the completion of the outer containment concreting. Now builders will have to install permanent parapets and close installation openings.

The reactor outer containment serves as physical protection against all external influences for the inner containment, which in turn ensures the leak-tightness of the internal volume with all operating conditions of the nuclear power plant, including emergency operations.

Thus, the Outer Containment will protect the reactor from natural and man-made external influences, including earthquakes, hurricanes, a plane crash. Therefore, especially strong reinforcement and high-class concrete are used in the construction of the outer containment.

Note:

Titan-2 Holding is the largest in the North-West group of companies, constructing the most important nuclear industry and power facilities. The company performs a full range of construction and installation works from engineering to commissioning.

Titan-2 Holding is the general contractor for the construction of the Leningrad NPP-2 power units. The Holding Companies perform all the civil, installation, and electrical works at a construction site. The works are carried out in the reactor, turbine, power supply, water supply, heat cogeneration buildings and other power unit structures.

Video news