Novy Urengoy, Yamalo-Nenets Autonomous District

Новый уренгой

The Group is performing a package of works for the installation of equipment for a new power plant. The main works are being carried out in the main building and air condensate unit, where the company’s specialists are installing process automation equipment and instrumentation.

The Company is also installing a power supply unit for electrified fittings and gas and steam turbine plant automatic control systems.

JSC SEM’s personnel is currently performing electrical installation works and is installing instrumentation and automated control systems in a polyethylene manufacturing unit under construction.

The works at the Gas Chemical Facility commenced in February 2013 and are to complete in December 2017. To date, JSC SEM’s specialists have laid more than 50 km of cable (control, power and fiber one), have tested and installed over 850 units of instrumentation and have installed about 100 stands and over 30 tons of metalwork.