Today fire fighting and temporary heating systems are being installed. This will enable safe work in the warm building during the winter.
The remaining few pieces of equipment of the first and second stage of reverse osmosis system will be lifted in order to be installed through the mounting opening in the roof of the building. After that, the heating circuit will be completely closed.
Six of the twelve tanks were installed in the open area of the water treatment tank facilities: two tanks of the source water, two tanks of partially demineralized water, and two demineralized water tanks. By the end of this year it is planned to deploy also two clear water tanks.
Currently, installation of stairs, railings and heating pipes on the tanks, and installation of supporting metalwork for the process pipelines are underway. Then process pipelines for the tank piping will be installed.
Note:
The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.
The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.