This is the first project in the line of modern medium-power national-design nuclear power units (VVER-600).
TITAN-2 Holding will perform a full range of construction and installation works, applying the experience gained in implementing complex nuclear projects in Russia and abroad.
The first two units of Kola NPP-2 with a power of 600 MW each are scheduled to be constructed from 2027 to 2037. The service life of the main equipment will be 80 years. In the future, the site involves the expansion by two more similar power units.
Igor Koshin, Director of the Kola NPP-2 Construction Program of JSC CONCERN TITAN-2: “For TITAN-2 Holding, participation in the Kola NPP-2 project is a significant stage and continuation of systematic work in the nuclear industry. We have the necessary competencies and practical experience in implementing complex infrastructure projects, we are ready to ensure the high-quality construction and installation of innovative VVER-S power units. I would like to distinctly thank all colleagues of the Holding – the signing of this prime contract was the result of the well-coordinated and professional work of the TITAN-2 team.”
The new NPP will strengthen the energy security of the North-West, where industry and port infrastructure are actively developing, and will become a driver of the social and economic development of the Arctic area.
For information:
The TITAN-2 Holding is a Russian group of companies that builds nuclear facilities. Organisations of the Holding perform the whole cycle of works, from development of basic design documentation to facility commissioning.
The TITAN-2 Holding is the general contractor for construction of the new power units of the Leningrad NPP. At the construction site, the organisations of the Holding perform all civil construction, installation, and electric installation works.
The Holding participates in the construction of Akkuyu NPP in Turkey, Paks II NPP in Hungary and El-Dabaa NPP in Egypt.