The future Pediatric Rehabilitation Center consists of three buildings connected by heated passages. It will include a 300-bed hospital, a treatment building with a clinical diagnostic center, and a day hospital.

Currently, works are underway on all buildings and structures at the construction site. Monolithic works are being completed in the main building. Installation of on-site water supply and heat supply networks is ongoing. Stonework of the building enclosure is in full swing. The company's specialists have begun installing window structures. Individual heating units for the hospital and the main building are being assembled.

In the near future, builders will have to close the thermal circuit of the buildings, complete roofing and façade works. In addition, they need to complete works on external networks and improve the territory.

Currently, about 500 people are involved in the construction site. The plans include increasing the number of personnel to 1,000 people and attracting additional 30 units of construction equipment. Completion of construction and delivery of the complex is scheduled for this year.

Denis Karasik, Director of the FPRC Construction Program, JSC CONCERN TITAN-2:

“JSC CONCERN TITAN-2 acts as the general contractor at the facility. This means that the company not only builds, but also purchases equipment and carries out commissioning works. Currently, the process of concluding contracts for the supply of elevator equipment is underway. Refrigeration and ventilation equipment is in production. Contracts for medical equipment have been partially executed. In close cooperation with the customer, we successfully resolve issues related to import substitution and optimize technical solutions in terms of the equipment used”. 

For information:

The TITAN-2 Holding is a Russian group of companies that builds nuclear facilities. Organisations of the Holding perform the whole cycle of works, from development of basic design documentation to facility commissioning.

The TITAN-2 Holding is the general contractor for construction of the new power units of the Leningrad NPP. At the construction site, the organisations of the Holding perform all civil construction, installation, and electric installation works.

The Holding participates in the construction of Akkuyu NPP in Turkey, Paks II NPP in Hungary and El-Dabaa NPP in Egypt.