At the end of last year, the main concreting works on all buildings of the center were completed. In total, more than 50 thousand cubic meters of concrete were used. Now the builders are reinforcing and installing the formwork of columns and walls, concreting the walls and floors at key facilities: the injector, the storage tank and in separate buildings of the experimental stations.

In the engineering support building, fire-protective coating is applied to the elements of the metal frame, metal structures are primed, brick walls and partitions are erected. In the test bench and testing building, the concrete base of the floor is being formed, facades, roofing, window frames are being installed, external walls and aerated concrete blocks are being laid.

Work is underway at 34 facilities of the complex simultaneously. The construction of the SKIF CUC is under the serious control of the Plenipotentiary Representative of the President of the Russian Federation in the Siberian Federal District Anatoly Seryshev. The facility will be commissioned this year.

For information:

The TITAN-2 Holding is a Russian group of companies that builds nuclear facilities. Organisations of the Holding perform the whole cycle of works, from development of basic design documentation to facility commissioning.

The TITAN-2 Holding is the general contractor for construction of the new power units of the Leningrad NPP. At the construction site, the organisations of the Holding perform all civil construction, installation, and electric installation works.

The Holding participates in the construction of Akkuyu NPP in Turkey, Paks II NPP in Hungary and El-Dabaa NPP in Egypt.