The work includes the construction of two 110 kV lines for the facility's own needs. Their length will be 5.5 km each, with 23 and 27 supports, respectively. Construction of two 220 kV lines is also underway. The first line, 5.7 km long, runs through the territory of Seversk, where 30 supports will be installed. The second line - 17.1 km, runs outside the city and consists of 80 supports. 220 kV is the power output of the BREST reactor facility.

Specialists from JSC SEM began work in August. To date, the volume of installation of 110 kV line supports has been fully completed; the wire has been installed by 60%. By the end of the year, the construction of a 220 kV power transmission line located in Seversk will be completed.

In total, about 40 people and 45 units of equipment are involved in the work. The construction of the power transmission line shall be fully completed in mid-2024.

JSC SEM continues to carry out electrical installation works at the site of the Proryv project, the entire volume of physical protection equipment and automated control systems is being carried out.

For information:

The TITAN-2 Holding is a Russian group of companies that builds nuclear facilities. Organisations of the Holding perform the whole cycle of works, from development of basic design documentation to facility commissioning.

The TITAN-2 Holding is the general contractor for construction of the new power units of the Leningrad NPP. At the construction site, the organisations of the Holding perform all civil construction, installation, and electric installation works.

The Holding participates in the construction of Akkuyu NPP in Turkey, Paks II NPP in Hungary and El-Dabaa NPP in Egypt.