More than a hundred CONCERN TITAN-2 specialists are working at the facility. They are modernizing the emergency core cooling system of the Armenian NPP Power Unit 2 reactor plant, in particular, replacing two high-pressure units with the low-pressure ones. The installation of new piping, replacement of electric cables and other works under Project are also being carried out.

Repair works have been started in mid-May and will be continued until October this year. Due to the modernisation the lifetime of the power unit will be extended.

Statement:

The TITAN-2 holding is a Russian group of companies that builds nuclear facilities. Organisations of the holding perform the whole cycle of works, from development of basic design documentation to facility commissioning.

The TITAN-2 holding is the general contractor for construction of the new power units of the Leningrad NPP. At the construction site, the organisations of the holding perform all civil construction, installation, and electric installation works.

The holding is the main contractor at the construction of the Hanhikivi 1 NPP in Finland and of the Akkuyu NPP in Turkey.