Over 600 company employees are currently operating at the facility.

The works are ongoing at the production and operation site housing the service building, checkpoint and repair shop. Here, the construction team specialists are arranging the bank using geonet. It is required for soil stabilization.

During the summer period, MSU-90 specialists arranged over 60,000 square meters of the bank, which makes 60% of the total scope. Works on cast cable tray and storm water sewage are 90% complete. The employees will further perform landscaping of this territory.

Works at process area or testing and treatment devices start-up site are ongoing. Equipment installation is 98% complete. Over 1300 joints were welded here by MSU-90 mechanical installation team.

Moreover, 12,000 cubic meters of concrete and 600 tonnes of reinforcement are installed at the testing and treatment devices site by this construction unit. Anchor blocks are concreted. MSU-90 specialists will also perform pipelines finishing painting.

Strict OHS, industrial and environmental safety requirements are followed at the facility. The company had no incidents with the loss of labor capacity through the whole working period.

Note:

Titan-2 Holding is the largest in the North-West group of companies, constructing the most important nuclear industry and power facilities. The company performs a full range of construction and installation works from engineering to commissioning.

Titan-2 Holding is the general contractor for the construction of the Leningrad NPP-2 power units. The Holding Companies perform all the civil, installation, and electrical works at a construction site. The works are carried out in the reactor, turbine, power supply, water supply, heat cogeneration buildings and other power unit structures.