By the end of the year, it is planned to complete the walls, assemble flooring and roof, and move on to utility networks installation and internal finishing works.

Following the schedule, metal structures and stands, subflooring and external networks (water supply, heating and sewage) are under site installation. JSC Concern Titan-2 and JSC MSU-90 specialists are performing the works. Electric installation company JSC SEM is getting prepared to install the power cable and arrange low current systems.

In order to ensure fire safety, special fire-proof coating is applied on the metal. Welding works are also underway. The facility is being prepared for the arrangement of the reinforced cast floorings and cast staircases.

Except from the arena, the volleyball centre will house gym, changing rooms, lunch rooms, recreation room, cloakroom and other amenities.

The facility is planned to be commissioned in the autumn of 2019.

Note:

Titan-2 Holding is the largest in the North-West group of companies, constructing the most important nuclear industry and power facilities. The company performs a full range of construction and installation works from engineering to commissioning.

Titan-2 Holding is the general contractor for the construction of the Leningrad NPP-2 power units. The Holding Companies perform all the civil, installation, and electrical works at a construction site. The works are carried out in the reactor, turbine, power supply, water supply, heat cogeneration buildings and other power unit structures.

The Holding is the main contractor for the construction of the Hanhikivi-1 NPP in Finland.