The work is performed by specialists of the Third Unit of JSC MSU-90. They are experienced installers who successfully completed installation of a turbine of the yet-to-be constructed LNPP Power Unit 1, which is now being prepared for commissioning.

All the components of the turbine were made in the St. Petersburg Company "Power Machines".

The turbine set is  a five-cylinder (four low-pressure cylinders, one high pressure cylinder), double flow

machine  with an electric power capacity of 1200 MW and speed of 3000 rpm. The total weight of the

steam turbine is over 2 500 tons.

To date, about 700 tons of the turbine body parts have been delivered to the site. Depreservation  and inspection of bearings No. 1-6, depreservation of the steam space of the low-pressure cylinders No. 2 and 3, as well as fitting in (scraping in) of foundation frames to the housings of bearings and to low-pressure cylinders No. 1 and 2 are carried out.

Previously, the specialists had installed all the supporting base slabs with a total weight of 15.9 tons. In addition, foundation frames were treated (scraped) both on the side of the permanent pads under the turbine set and on the side adjacent  to low-pressure cylinders No. 2 and 3.

In the near future specialists of JSC MSU-90 will start the erection of the casings of low-pressure cylinders No. 2 and 3. An overhead crane with a lifting capacity of 220 tons will be used for the lifting operation.

Note:

The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.

The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.