Specialists of JSC MSU-90 and JSC Northern construction department conducted the operation of lifting the large-size equipment.

Installation of the steam generator on its regular place was carried out using an open top method, that is, through the open roof of the building. This method allows to simplify the mounting process and to speed up the process of construction as a whole.

The 320 t steam generator was raised with the crane "Liebherr LR 11350" to a height above 40 meters and lowered inside the reactor building to a level of +16,000, on the special supports.

The remaining three steam generators and the pressurizer will be mounted in the same way. These are the main process equipment of the reactor plant. The steam generators are designed to generate steam that drives the turbine.

After installation, each piece of equipment will be covered with a special metal sectional casing to ensure protection against external effects. This will enable specialists to continue construction and installation work in the reactor building prior to covering it with the dome.

Note:

The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.

The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.