The system connects the turbine to the evaporative cooling towers via pump station and intake channels.

The final stage of work on this site will be waterproofing of the cooling towers pools. This is necessary in order to protect concrete from external effects and to ensure the strength of building structures.

The volume of each pool is 24 thousand cubic meters, their depth being approximately two meters. In order to  apply the waterproofing each pool has to be drained. The work will be carried out by specialists of the "Northern construction department".

Waterproofing application in one of the pools will be started soon. After cold and hot run the specialists will perform waterproofing of the second pool. The work is scheduled to be completed by mid-October.

Note:

The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.

The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.