After works on alignment of the shaft of the turbine unit have been finished in the turbine building of the first power unit of LAES-2 under construction, specialists of JSC "MSU-90" have started dismantling of the low-pressure cylinder.
In order for the cylinder to lean against foundation support frames in regular intervals, its case is suspended at first, then a cover is hung on it and then steam exhausts are welded to the condenser. During the following stage of works, diaphragms are placed in the bottom part of the low-pressure cylinder and the flowing part of the turbine unit is formed.
Note:
The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.
The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.
Works in the turbine building
- Details