About hundred cells have already been installed in the building. The total number of the cells in the facility will be 132. Installation of steel structures for laying of electric cables is coming to the end.

Construction electricians of area no.4 are finishing installation of earthing circuit and lighting systems. Installation of lightning protection system on the building roof will be the next step.

Note:

The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.

The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.