Specialists of JSC CONCERN TITAN-2 have completed installation of metal structures of the first power unit crucial facilities.
The turbine building frame with a total weight of over two thousand tons and the heat cogeneration plant frame are fully mounted. The total mass of the latter made up 250 tons.
The turbine frame installation took five months, the heat cogeneration plant frame installation was completed in 45 days. Metal structures were installed with the MANITOWOC 18000 crane, specially delivered to the construction site from Sosnovy Bor.
Currently, over six hundred people work in a stand-alone division of JSC CONCERN TITAN-2 in Kurchatov. They are constructing turbine island facilities at the first and second power units of Kursk NPP-2.
Background Information:
Holding TITAN-2 is a Russian group of companies building nuclear facilities. Holding companies perform a full cycle of work - from the development of design documentation to the commissioning of the facility.
Holding TITAN-2 is a general contractor for the construction of new power units of the Leningrad Nuclear Power Plant. Holding companies perform all general construction, installation and electrical work at the construction site.
The Holding is a main contractor for the construction of Hanhikivi-1 NPP in Finland and Akkuyu NPP in Turkey.
TWO MILESTONE EVENTS AT THE KURSK NPP-2 CONSTRUCTION SITE
- Details