They saw how weekly facility rounds are performed and learned about the current stage of the sports center construction.

The tour was arranged under the cooperation of the college and the “Titan-2” Holding. The company takes students for the production practice and in future is willing to employ the graduates permanently.

JSC “Concern Titan-2” acts as the General Contractor for the volleyball center construction. All the Titan-2 subsidiaries and several subcontractors are involved into the project.

As of now, volleyball center floorings are arranged. The installation of sandwich panels is almost over. Stained glass panel structures are already installed onto the facades. It is planned to commence glazing next week.

Roof structures are 80% ready, stands assembly is almost over. Specialists commenced installation of the utility networks and firefighting system.

The facility is planned to be delivered in autumn 2019.

Note:

Titan-2 Holding is the largest in the North-West group of companies, constructing the most important nuclear industry and power facilities. The company performs a full range of construction and installation works from engineering to commissioning.

Titan-2 Holding is the general contractor for the construction of the Leningrad NPP-2 power units. The Holding Companies perform all the civil, installation, and electrical works at a construction site. The works are carried out in the reactor, turbine, power supply, water supply, heat cogeneration buildings and other power unit structures.