This operation was fulfilled by the specialists of SMU-1 and UMiAT of the Northern Construction Department. Two hoisting cranes Grove were used for assembly works and test loading.

The metalwork manufactured by JSC MSU-90 weighs 10.990 tons. To check the spread beam under workload a weight of 250 tons was attached to it.  By means of crane Liebherr 11 350 it was lifted to a height of 100 mm in order to be under workload during the time specified by the regulatory documents.   The actual load during installation of the 4-th tier of inner containment will be 200 tons.

At present PJSC SUS specialists are making preparations for installation of this huge metalwork. At the moment the metalwork is on a special site where it has been preassembled near the Power Unit 2 reactor building of the LNPP under construction. All welded joints were tested for defects using ultrasonic method with subsequent inspection for leaks, and accepted by a commission consisting of specialists of the Customer, General Contractor, representatives of JSC "ATOMPROEKT" and Subcontractor.

Note:

The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.

The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.