Experts of JSC CONCERN TITAN-2, the contracting organization of the LNPP under construction, completed the installation of main and auxiliary equipment of technological systems in the standby diesel-generator station building of the first power unit. At present post-installation cleanup and tests are under way.

The standby diesel-generator station building houses four diesel-generator sets. Each set has a length of 12 meters, width of 4 meters and height of 4.5 m. Weight of one piece of equipment is 140 tons. To date, all four emergency power system diesel-generators are in their regular places. The standby diesel-generator station building has been powered according to the standard operation diagram.

Currently, work is under way at the first and second bays of the standby diesel-generator station. For the first bay purging and testing of lubrication systems, complete flushing of the cooling system, purging with compressed air of the start air and  fuel system  were performed and tests were started as well as  commissioning of the measuring channels. These works and the installation of the exhaust system and air intake system for both channels are scheduled for completion by the end of February.

After finishing commissioning works together with the experts of JSC "ATOMTECHENERGO" under the supervision of engineering supervisors from the manufacturer of the equipment "Wartsila Finland OY" and "Leroy Somer" a comprehensive test of two diesel generators (at the rated power and load) will be conducted. The tests shall confirm the equipment readiness for beginning  of cold-hot trial phase of the power unit equipment, which is scheduled for March 2017.

Note:

The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.

The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.