One of the trestles connects Heating plant building with the first and second power units of the nuclear power station. At this facility the company's employees assembled metalwork – beams and pedestrian overpasses. Al in all there are some 300 tons of steel and 90 tons of pipes 25 to 1020 mm meter in diameter.

To date, the work on this project has been mostly completed.

Another trestle that is being installed by specialists of "MSU-90" links the building of Power Unit 1 turbine with a steam chamber that will provide putting the equipment into operation.

LBG system, a pipeline 426 mm in diameter, is laid out on this trestle, to deliver steam to the turbine. Specialists of the second unit pre-assemble the pipeline on a special platform. Then with the use of a truck crane the enlarged portions are mounted on the trestle having a height of approximately 9 meters. The installation is carried out with the use of an aerial work platform.

Pipes were manufactured at the production complex "MSU-90". The length of a branch of the pipeline is 25-30 meters. It weighs approximately 400 kg. To date, 30% of the work has been done.

Note:

The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.

The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.