This is an important object of Leningrad NPP under construction, which has a high degree of readiness. Some of the equipment have been already energized. During 2016 the works here were conducted by specialists of the fourth unit of JSC "SAM". They fully assembled the equipment of the building. More than 70 employees were involved in the works at the facility.

The Relay panels building is intended for 330 kV and 750 kV gas insulated switchgears automatics relay protection. The relay panels are in the room at approximately 4,350. They are cabinets with a height of two meters and a width of 60 cm. Each cabinet weighs approximately 200 kg. Rows of panels are placed on a special raised floor, under which all cable connections were laid.

The high-tech equipment was loaded in the building by a crane truck and lifted to the second floor with the use of a winch. All in all there were 140 relay panels installed. Now the relay panels are under commissioning in their room. JSC “SAM” have already fulfilled all main work for the project.

Also specialists of JSC "SAM" have assembled cable metalwork at around -3,600 and laid out hundreds of meters of cable thereon. They also laid out cable in the two underground tunnels to connect the  relay panels building with  a metal clad switchgear ( 330 GIS) and a 10 kV overall plant auxiliary switchgear (10 kV auxiliary switchgear).

One cable line is as long as 1000 meters. At present the works including cable products necessary for testing have been fully completed.

Note:

The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.

The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.