Two main circulation pump sets have been delivered to the construction site of the Leningrad NPP. Specialists of the First Unit of JSC “MSU-90” unloaded the equipment near the reactor building of the second Power Unit.

The equipment will be installed in the reactor building at level +14,000. There will be four such pumps altogether. They are intended for providing coolant circulation in the primary circuit and heat removal from the reactor core.

Each of the pumps weighs 60 tons. Complete with the electric motor the pump weighs over one hundred tons. According to the schedule the equipment shall be installed to its standard place next month.

Note:

The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.

The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.