JSC "CONCERN TITAN-2" is the  construction contractor. Currently, tree removal is underway at the area of the construction site. Within a month, specialists will have to clear the area from vegetation and to prepare the site for earthworks. The completion of the center construction is scheduled for the  fall of 2019.

The operations involve specialists of the NPP, servicemen, and representatives of the  holding TITAN-2 subsidiary,  JSC MSU-90, who installed the equipment of the reactor plant.

Today fire fighting and temporary heating systems are being installed. This will enable safe work in the warm building during the winter. 

The work is performed by specialists of the Third Unit of JSC MSU-90. They are experienced installers who successfully completed installation of a turbine of the yet-to-be constructed LNPP Power Unit 1, which is now being prepared for commissioning.