The electric motor was transported, assembled and installation by specialists of JSC MSU-90.

It is the first of four electric motors of the reactor coolant pump (RCP). Their purpose is to circulate the coolant in the primary coolant circuit and to dissipate heat from the reactor core. Each electric motor weighs 46 tons. It was mounted at the level mark of +14.500.

Three remaining electric motors are planned to be delivered, assembled and installed to their standard places in July. Then the electric motors shall be connected to all pipelines.

Note:

The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.

The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.