Electrical installation works are performed by specialists of JSC SEM; JSC CONCERN TITAN-2 subdivision for the construction of facilities with own resources is getting ready to operate on the site.

Currently, construction base temporary buildings and structures are being constructed. Construction of the reinforcement shop is started, and construction of two buildings of the administrative complex is at the completion stage. Moreover, contract for paint shop construction is awarded.

Construction of an accommodation camp for one thousand employees is completed. The camp is fully ready for accommodation. The first to move in will be JSC SEM specialists and constructors of JSC CONCERN TITAN-2. This year, JSC CONCERN TITAN-2 is going to start construction work with its own resources. Subdivision’s specialists will start foundation preparation and concrete work for storage facilities.

Dredging works are underway in waters of the Gulf of Bothnia. Construction of water intake facilities is ongoing. Current completion status for the southern breakwater is 90%; northern breakwater will be completed this year. Next year, a jetty and culverts will be erected for additional water supply to the intake facilities and protection of water intake area against ice, among others.

Note:

Titan-2 Holding is the largest in the North-West group of companies, constructing the most important nuclear industry and power facilities. The company performs a full range of construction and installation works from engineering to commissioning.

Titan-2 Holding is the general contractor for the construction of the Leningrad NPP-2 power units. The Holding Companies perform all the civil, installation, and electrical works at a construction site. The works are carried out in the reactor, turbine, power supply, water supply, heat cogeneration buildings and other power unit structures.